September 28, 2026
Woodland Hills Elementary School Construction Update - September 28, 2026

Construction activities continue to progress at Woodland Hills Elementary School, with several key milestones recently completed and upcoming work underway.
During the week of September 21, crews:
- Began concrete foundation work
- Include elevator pit footings and walls
- Minor grade cuts at the south end of the site
- Coordinated masonry layouts for elevator and structural walls
Upcoming work:
- Continuing the installation of footings, elevator pit, and walls with concrete
- Begin in-ground sleeves for electrical and plumbing work
- Continue sleeving with footings with trade partners.