District-wide Bond Project Update - Week of November 2, 2026

Here’s the latest on the ongoing construction projects taking place at KCKPS:
Argentine Middle School
Crews have worked on the following:
- Footing excavation and concrete pours
- Plumbing sanitary line/in-ground installation
- Completed NE parking lot for laydown and construction parking
- Masonry mobilization
Upcoming construction activities
- Structural masonry will ramp up
- In-wall plumbing and electrical installations
- Continue footing, form work, and other foundation work
Central Middle School
Crews have worked on the following:
- Footings and foundation walls
- Underground plumbing and electrical
- Prep and pour slab on-grade
Upcoming construction activities
- Door frame installation
- North parking lot curbs and asphalt base
- Crane road installation
- Load bearing CMU walls